| |
 |
Our
Customers - Willerby Holiday Homes |
Established
just after the Second World War, Willerby, with a turnover in excess
of 100m and employing 650 employees at its site in Hull, UK is the
market leader in the construction of Holiday Homes. Using skilled
craftsmen and traditional build methods and materials, the workforce,
working in departmental Silos, have been driven by a culture of 'the
more the better'.
When Willerby needed to invest in a replacement scheduling system,
it knew that only the most competent of scheduling solutions would
suffice. Willerby found that solution in Preactor APS, provided by
Preactor Solution Provider, RMS.
Business
Challenges
The work which goes into each of the Holiday Homes which leave
one of Willerby's three assembly lines every 30 minutes is vast.
Working with large batch sizes, a 6 week production lead time,
and 150,000 machined parts of huge variance each week, Willerby
consequently faces major business challenges.
|
|
Unsurprisingly, bottleneck processes were hard to identify, rework
and missing parts were common and the 11th hour subcontracting of
some components was a frequent occurrence. Moreover, the 3 shift system
in the machining centre left no room to gain any spare capacity so
new machinery was bought and installed wherever there was space. Different
areas also provided specific challenges which combined to give the
company major problems, as Craig Dunn, Lean Operations Manager, explains.
As
Willerby
Homes produced Holiday Homes of varying cycle times across three assembly
lines, each with a different number of working bays, MS Access could
not produce accurate schedules. As products moved through these bays,
models with a different cycle time would follow them. If a faster
product went on the line behind a slower product it would have to
move at the speed of the product in front until the last of these
left the assembly line. It was only at that point that the faster
product could move at its own cycle time. On the other hand, if a
fast product was moving down the assembly line followed by a slow
product, a natural gap would manifest and grow as products worked
their way through each bay. This was the main cause of the schedule
inaccuracy, as the access program did not account for this anomaly.
Although very profitable, there was a realisation that this batch
and queue method combined with a disorganised and inflexible style
of working would not equip the company for future success. As Willerby
intended to stay at the top in its field with a desire to set standards
in the industry by becoming a World Class Manufacturer, the company
realised it needed to instigate changes.
A Lean Manufacturing approach was targeted
as the way forward but first it had to understand and gain control
of its processes. This was a long hard road that was to take
some five years to complete but would allow Willerby to move
into the visual shop floor environment.
|
|
The
Solution
With this in mind, the company, which at this point had no central
planning function, visited the CIM show at the NEC. In their search
for scheduling software they asked various MRP and ERP vendors for
recommendations. The common response was to check out Preactor which
the majority were already using with their own product. After talking
to Preactor Solution Provider RMS and being impressed by the software
they took this information back to Colin Jeffrey, Willerby's Production
Director. From there the decision was made in early 2000 to select
Preactor APS as the way forward.
Production Director Colin Jeffrey
believed
it to be the best software on the market offering the right
solution and flexibility. This was based on many case studies
and other literature, including articles found in The Manufacturer,
which convinced me that there was no better product out there
that would better satisfy our needs. We were unable to start
a Lean implementation program without first understanding and
gaining control of our processes and Preactor offered the solution".
|
|
Implementation
and Benefits
The first step of the implementation focussed on increasing the
accuracy of the assembly line schedule and began late 2000 after
RMS had installed and set up Preactor and delivered the necessary
training. Dunn explains. "Preactor wasn't capable of reflecting
the changeover anomaly that we were experiencing on the assembly
lines through its standard functionality, so RMS was called back
and briefed with the problem. They then went away and carried out
various paper simulations in an attempt to understand the logic
and mathematics of what was happening. Once this had been established,
RMS customised Preactor in an appropriate way."
With
the work now done on the assembly lines, schedule accuracy had risen
from 80% to 95% and working closely with Willerby's staff, RMS also
linked this Preactor model with the MRP system taking away the need
for keying in data each week. This stabilised the supply chain. Once
the assembly lines were sorted, Willerby then focussed on the supply
areas, beginning with the machine shop. This carried massive inventory
and had no real workflow. Working with the machine shop manager, the
process of building a Preactor system started to give an understanding
of this work centre. This process was difficult as shop floor knowledge
had always driven the process and there was little documented data
to build a system with.
Ian
Shufflebotham, General Manager describes how this was overcome.
"In the absence of clear data we had to collect as much information
from the shop floor personnel as possible including routing information
and operation times. This gave us the foundation to simulate the
shop floor activity through Preactor which quickly allowed us to
see where our bottleneck and problematic areas of concern were."
Dunn
explains the benefits this brought. "Using this new knowledge
and creating 'what if' scenarios in Preactor it allowed us to create
flow by rerouting products and moving machinery. The WIP was reduced
to sensible levels and efficiency was maximised. Subcontracting,
once a common occurrence, ceased and the 3 tier shift pattern in
this area was reduced to 2. Lead times were slashed and the MRP
system was brought in line reducing the amount of bought in stock
carried in storage."
With better schedule accuracy and control of the machining processes,
things became much clearer. In the absence of inventory on the shop
floor, visibility was created and the number of missing and damaged
items dropped to a handful. Bottleneck processes were easily identified
by Preactor and contingencies were discussed months in advance.
But
the assembly lines were still held up waiting for supply from one
particular subassembly area, the Jig Shop. This section hand made
the sidewalls and bulkheads for the main construction of each Holiday
Home. This area was constantly starving the assembly process and the
operatives would work extensive overtime in an attempt to satisfy
demand. There was no scheduling or balanced workflow in this area
and operatives were left to sort through and create their own work
plan with each resource not fully aware of their working colleague's
activities.
A
Preactor scheduling system was implemented to put order in this
part of the business. Schedules were created in advance for
each resource which was given 'work to' lists, and a calmer,
more fluid environment began to take hold.
|
|
Further
work and Challenges
Five years after its installation,
Preactor has brought about some incredible changes. Dunn again, "Production
Leads are now down from 6 weeks to 5 days and WIP has been reduced
by a massive 80%. Subcontracting has ceased and we are now capable
of producing the same volumes on a two shift system in the machine
centre. Various 'what if' scenarios have helped us replan our layout
and provide better workflow, increasing efficiency and gaining capacity.
Overtime, once abundant, is now minimal and Managers now find the
time to manage".
"Lending itself to fit into any environment through its easy
configuration and visual depiction of workflow through Gantt charts,
Preactor has provided us with the means to start applying Lean philosophies
to the business. Although still providing scheduled work to some areas,
Preactor is now being reconfigured to produce capacity planning for
the management team in some supply areas."
Interfaced with
Willerby's MPS system, Preactor is still scheduling the main assembly
lines and drives the MRP process and the balance is now being found
between Lean Kanban control and finite scheduling.
Mike
Novels of Preactor International concludes:
"This
is an excellent example of how scheduling tools, customised to meet
the unique challenges of each business, can work together with traditional
lean control techniques to provide the solution that companies need
to become World Class in their sector."
|